Heritage Trail East Construction and Master Plan Update
Summary
Approval of a $6.59 million contract to Patin Construction to bridge the gap in the Heritage Trail between Mays and Georgetown streets, completing a major east-west pedestrian corridor.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 2 meetings in the last 60 days; most recently Sep 10, 2026.
Impact analysis
Capital project expenditure of $6,591,000.
Trail users and downtown visitors seeking safe, off-street connectivity.
No groups negatively affected
Mentions & discussions (4)
City Council — September 10, 2026
Approval of a $6.59 million contract to Patin Construction to bridge the gap in the Heritage Trail between Mays and Georgetown streets, completing a major east-west pedestrian corridor.
City Council - Packet Briefing — September 8, 2026
Patent Construction was selected as the low bidder for a $6.5 million project to build the Heritage Trail East gap between Mays and Georgetown streets, backed by a $6.3 million TxDOT grant.
Round Rock adds new tennis courts, continues playground construction at Old Settlers Park
Round Rock adds new tennis courts, continues playground construction at Old Settlers Park KEYE
Round Rock in process of building the City's largest playground in Old Settlers Park
Round Rock in process of building the City's largest playground in Old Settlers Park KEYE
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Round Rock
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.