Wastewater Treatment Plant No. 2 Aeration Basin Rehabilitation
Summary
A 60-foot clarifier that's been out of service is getting an $866,750 fix, restoring treatment capacity the plant has been lacking.
At a glance
- Total mentions
- 3
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 3, 2026.
Impact analysis
Paid from the water/wastewater fund โ the same fund your water bill feeds โ with no general tax hit.
Water and sewer customers citywide, since the fix restores lost plant capacity.
Mentions & discussions (3)
City Council Regular Meeting โ November 3, 2026
A 60-foot clarifier that's been out of service is getting an $866,750 fix, restoring treatment capacity the plant has been lacking.
City Council Regular Meeting โ September 1, 2026
The city awarded a $4.5 million contract to expand sewage treatment capacity from 25,000 to 95,000 gallons per day. The project supports future growth and includes cost-sharing with Lamar Consolidated ISD.
City Council Regular Meeting โ January 20, 2026
The city is hiring a contractor to clean and repair the aeration basin at Wastewater Treatment Plant No. 2 to improve energy efficiency and treatment quality.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Rosenberg
What the council decided, in plain English โ one email a week.
Free. Unsubscribe with one click any time. We never sell your email.