Cecil Drive street reconstruction
Cecil Drive scored poorly in the survey and will get a full rebuild — road, water and sewer — designed now with bids in August and construction starting in September.
Citywide street conditions and paving priorities
The new AI street survey scored Richland Hills pavement 48/100, with the worst roads — Cecil, Mimosa Park, Ruth Road — concentrated on the south side. Council wants the maps public so residents understand costs and why the sales tax measure matters.
FY27 Street Mill and Overlay Program
The street sweeper program isn't delivering — council discussed dropping it after paying $10,000 for disappointing results. Public Works also plans a smaller roller (under $30,000) so crews can do better pothole repairs without a CDL driver.
Mimosa Park Drive Mill and Overlay
The 2600 block of Mimosa Park Drive — already upgraded with a new water main, sewer pipe bursting, and new curb — gets a county mill and overlay at about $60 per linear foot versus $150 by contract, targeted for mid-July.
Five-Year Capital Improvement Program
Staff pitched a data-driven scoring system — nine weighted criteria including public safety (25%) and regulatory compliance — to rank capital projects objectively. A framework resolution comes back June 22, with the full five-year CIP up for a vote in late July.
Street Project Funding Reallocation: Glenview vs. Booth Calloway
The city is asking Congress for $6 million to rebuild Booth Callaway Road and replace utilities — the street literally splits two congressional districts, which staff see as a plus.
Ending the Real Time Transport Program
About 11-14 residents — some with intellectual disabilities — use the city-subsidized ride service each month, at roughly $25 per ride and over $5,000 monthly. Council set a hard stop date of July 24, 2026, and staff will personally deliver notices with alternative options like Catholic Charities.
Right-of-way stakes on Kingsbury Avenue property
Resident Sid Wright says survey stakes marked ROW are deep in his yard with no city notification, reviving a 12–15-year-old right-of-way question tied to old federal sidewalk grant funding. He asked the city to resolve it before any work begins.
Glenview street project possibly paused
The Glenview reconstruction could cost $5 million in city funds; the city manager asked whether a cheaper mill-and-overlay could work instead while revenues are weak.
Freeway noise walls
Residents near Handley deal with deafening traffic noise and have asked TxDOT for a sound wall for about ten years — it was skipped on the residential stretch in prior phases.