SCADA Remote Site Monitoring Contract Correction
Summary
City staff uncovered a multi-million dollar bidding and administrative error in a major water SCADA system contract, resulting in a $2.56 million contract reduction that saved funds for the utility department.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 1, 2026.
Impact analysis
Reduces the project contract cost by $2,563,104.56.
Water and wastewater ratepayers and the City of Kyle utility fund.