Paul Davis Park Trail Improvements
Summary
A Texas Parks and Wildlife grant-backed trail at Paul Davis Park is moving into design, with hopes of construction by May or June. The city budgeted $166,000 total with a $33,000 match.
At a glance
- Total mentions
- 4
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 7, 2026.
Impact analysis
Design work is roughly $27,000 including an optional environmental portion, out of a $166,000 project budget with a $33,000 city match.
Residents and park users who will get a new trail, possibly by summer.
No groups negatively affected
Mentions & discussions (5)
City Council - Oct 7, 2026
A roughly half-mile, 6-foot-wide decomposed granite trail got funded with a $159,000 contract award, mostly covered by a state parks grant. Construction should run 45-60 days starting late October.
City Council - Jul 1, 2026
A resident praised the park's mowing and clean restrooms but flagged food debris and cruddy concrete in the main pavilion, asking for a power wash. Public Works has been prepping the park for July 4th.
City Council - May 11, 2026
The trail design is finished and the city can now hire a contractor. Construction should start mid-to-late July, after the Fourth of July event.
City Council - Jan 7, 2026
A Texas Parks and Wildlife grant-backed trail at Paul Davis Park is moving into design, with hopes of construction by May or June. The city budgeted $166,000 total with a $33,000 match.
Garden Ridge receives grant funding for new trail at Paul Davis Park
Garden Ridge receives grant funding for new trail at Paul Davis Park Community Impact Newspaper
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Garden Ridge, TX
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.