Water Use and Data Centers
Summary
El Paso's water chief is worried about a new Meta data center guzzling water. He's saying we can't keep approving these massive water-sucking projects if we want to have enough water for everyone else.
At a glance
- Total mentions
- 9
- Last 30 days
- 1
Impact analysis
Basically, approving more data centers could mean higher water bills for all of us down the line.
Tech companies like Meta get to build their data centers, but at what cost to our water supply?
All El Paso residents could face water shortages or higher costs if we don't manage this carefully.
Mentions & discussions (20)
Hundreds of Texas data centers under investigation after failing to report water usage
Hundreds of Texas data center developments were under investigation after failing to report water usage.
Oracle partnership to use sensor tech to boost water efficiency
EL PASO, Texas (KTSM) -- Oracle announced its partnership with an agriculture technology company to conserve about 21 million gallons of water annually, more than the water that will be used for Project Jupiter. "This is more than 20 times the amount...
Meta data center town hall turns tense as residents press water, power officials
Meta data center town hall turns tense as residents press water, power officials KFOX
City requests statewide data center ratepayer protections
EL PASO, Texas (KTSM) — The City of El Paso has submitted formal comments to the Public Utility Commission of Texas (PUCT) requesting that ratepayer protections be applied statewide, including to communities served by utilities outside the Electric R...
City calls on state officials to extend data center ratepayer protections to El Paso
City calls on state officials to extend data center ratepayer protections to El Paso KVIA
City requests statewide data center ratepayer protections
City requests statewide data center ratepayer protections KTSM 9 News
'Block Party' protests Meta data center in Northeast El Paso
Community members and activists held a protest on Saturday, July 25, in Northeast El Paso to voice opposition to a proposed Meta data center project over concerns regarding health, noise, and water consumption.
Texas lieutenant governor candidate calls for special session on data centers
EL PASO, Texas (KTSM) -- State Rep. Vikki Goodwin, D-Austin, who is the Democratic nominee for lieutenant governor, called for a special legislative session on Tuesday, July 14 to address what she calls the "growing data center crisis facing Texas." ...
Data centers become flashpoint in gubernatorial races
“Could you invent an easier political target if you tried?”
Meta data center water cap set at 2.5M gallons a day; average pegged at 480,000
Meta data center water cap set at 2.5M gallons a day; average pegged at 480,000 KFOX
City council to discuss water use, infrastructure for Northeast, Meta
EL PASO, Texas (KTSM) — The El Paso City Council will hold a work session on Monday morning, July 6, to review a presentation then discuss water and infrastructure planning for Northeast El Paso, including projected water use at the Meta data center ...
NM lawmakers push for statewide moratorium on data center projects
EL PASO, Texas (KTSM) -- A handful of state lawmakers from Southern New Mexico want to place a statewide moratorium on large-scale data center developments across the state. State Reps. Micaela Lara Cadena (D-Mesilla), Angelica Rubio (D-Las Cruces) a...
'Listening Session' on data centers in NM set for August
EL PASO, Texas (KTSM) -- A joint Legislative Listening Session on data center projects, including the controversial Project Jupiter in Doña Ana County, has been scheduled for next month. The event will be held from 6 to 8 p.m. on Tuesday, Aug. 11 at ...
City Council Seeks to Support Texas Governor Abbott in Protecting Utility Ratepayers from Datacenters and Create an Agreement with META to Benefit El Paso
City Council Seeks to Support Texas Governor Abbott in Protecting Utility Ratepayers from Datacenters and Create an Agreement with META to Benefit El Paso El Paso Herald Post
El Paso Rep. Boyar Trejo faces recall petition after vote on Meta data center incentives
El Paso Rep. Boyar Trejo faces recall petition after vote on Meta data center incentives KFOX
City of El Paso opposes $551.8M power plant for Meta data center
City of El Paso opposes $551.8M power plant for Meta data center KTSM 9 News
Northeast El Paso representative Boyar Trejo faces recall petition over Meta vote
Northeast El Paso representative Boyar Trejo faces recall petition over Meta vote KTSM 9 News
JPMorgan’s dual role at El Paso Electric, Meta El Paso data center
JPMorgan’s dual role at El Paso Electric, Meta El Paso data center Private Equity Stakeholder Project PESP
Photos: Crowd packs City Council, opposes data center water use
Photos: Crowd packs City Council, opposes data center water use El Paso Times
El Paso Residents Voice Concerns Over Rapid Rise of Data Centers in Borderland region
El Paso Residents Voice Concerns Over Rapid Rise of Data Centers in Borderland region KTEP 88.5 FM
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for El Paso
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.